Blog
The Gateway tunnel and the 2026 funding pause
What stopped the Hudson Tunnel Project in February 2026, how $205 million got it moving again, and where the $16 billion rail tunnel stands now.
On a normal weekday, every NJ Transit train that goes to New York Penn Station and every Amtrak train between New York and the south passes through the same pair of holes in the ground. They are the North River Tunnels, two single-track tubes under the Hudson that opened in 1910. They are old, they are the only passenger rail link between New Jersey and Manhattan, and they were soaked with salt water when Hurricane Sandy flooded them in October 2012. The corrosion that followed is the reason a new tunnel is being built.
In early February 2026, work on that new tunnel stopped. About 1,000 workers who had been building the Hudson Tunnel Project stopped working on February 6 when the project's federal reimbursements dried up, and for about two weeks one of the largest infrastructure projects in the country sat idle. By the end of the month the money was flowing again. This is what happened, who said what, and what has changed since.
What the project is
The Hudson Tunnel Project is the centerpiece of the Gateway Program, the plan to double rail capacity across the Hudson River. It is being built by the Gateway Development Commission, a body created by New York, New Jersey and Amtrak. The project's cost is about $16 billion. The central piece is a second two-track tunnel under the river, with the target of finishing it around 2035. Once the new tunnel is in service, the 1910 tubes can be taken out of service one at a time and rebuilt, something that cannot be done now without cutting the rail link in half.
That last point is the heart of the case for the project. The two existing tubes carry every train between the states, so a closure of either one for a complete repair would cut capacity sharply. Until a second crossing exists, the old tunnels have to stay open and decay slowly. The new tunnel is not an addition so much as a way to make repair possible. NJ Transit and Port Authority of New York and New Jersey are the two main New Jersey agencies tied to the project's service and funding.
How the work is divided
The project is built under several large contracts, each a different part of the line. The Palisades Tunnel, the first package, was awarded in 2024. The Manhattan Tunnel package, a $1.18 billion contract, went to a joint venture of Frontier-Kemper and Tutor Perini in 2025. And on April 27, 2026, the Gateway Development Commission's board, meeting in Newark, approved the last big tunneling contract: a $1.29 billion award to a Traylor, Walsh and Skanska joint venture to bore roughly 1.5 miles of twin tunnel under the Hudson itself.
The Hudson River section is the hardest part. The tunnel boring machines have to pass through a mix of rock, soft soil and ground that has been stabilized in advance, under a river that carries ship traffic and a heavy tidal flow. With that award, all of the tunnel boring and heavy civil construction on the project was either awarded or underway. A separate $711.7 million contract for the New Jersey surface alignment, the approach on this side of the river, went to a Skanska Creamer Sanzari joint venture and was approved on June 1. In September 2026, a television report counted seven of ten construction contracts as complete or underway.
The pause
The freeze did not start in February. It began the previous fall. In September 2025, the federal administration froze funding for the project, saying it wanted to review contracting practices under what it described as unconstitutional diversity principles. The commission said it had complied with the administration's questions about how contracts were awarded. For months the project kept working by spending down its own resources and drawing on a line of credit.
Then the money ran out. The commission said it had exhausted its line of credit, and by February 6, 2026, work stopped. About 1,000 people were sent home. Both states and the commission went to court, and the dispute became a national story, in part because the project is one of the largest transit construction efforts in the country.
The money came back in pieces. A first release of $30 million was announced on February 13, and on February 18 the commission said that the federal government had released the remainder of the $205 million it was owed, giving it more than $205 million available to pay for work. It said it had now received the full reimbursement owed to it. The commission sent letters to its contractors and said work would resume the following week. On March 12, a federal claims court judge ruled that the main lawsuit was largely moot, since the government had released the funds the case was about, though the commission had said in February that it would keep pressing for full access to federal funding.
The two sides described it differently. The federal administration's stated reason was a review of how contracts were awarded, and it said the funds were under that review. The commission said it had answered every inquiry. The states argued in court that the funding agreement obliged the government to reimburse work already done. What is not in dispute is the timeline: payments stopped, work stopped, a court fight followed, and money began to move again in the second half of February.
The timeline
| Date | Event |
|---|---|
| 1910 | The North River Tunnels open |
| October 29, 2012 | Sandy comes ashore near Brigantine and floods the tunnels with salt water |
| September 2025 | Federal funding for the Hudson Tunnel Project is frozen for a contracting review |
| February 6, 2026 | Work stops as the project runs out of money; about 1,000 workers idled |
| February 13, 2026 | A first release of $30 million is announced |
| February 18, 2026 | The commission says the remaining $205 million has been released |
| March 12, 2026 | A federal claims judge rules the main lawsuit largely moot |
| April 27, 2026 | The board awards the $1.29 billion Hudson River boring contract |
| June 1, 2026 | The $711.7 million New Jersey surface alignment contract is approved |
The Sandy line deserves a sentence of its own. The storm that wrecked the Seaside Heights boardwalk also sent the harbor into the tunnels, and salt water does lasting harm to the concrete, cables and signal equipment inside a rail tube. Sandy, October 29, 2012 tells the storm's story, and the tunnel is one of its less visible legacies. The Gateway project exists, in practical terms, because the old tubes were hurt faster than they could be repaired.
Two numbers to keep in mind
Two figures from the story help put the pause in perspective. The first is $16 billion, the project's total cost, of which nearly $2 billion had been spent by February 2026. A stoppage in the early years of a project that size can look small against the full budget, but it falls on the part of the budget that is already committed to contractors. The second is 1,000, the number of people working on the project when the money ran out. That is the number the commission pointed to when it described the effect on the ground, and it is the number the commission expected back on the job once work resumed.
Neither figure says who was right in the dispute. They say what was at stake: a long, expensive job that depends on a steady flow of money, and a workforce that depends on the job.
What the pause cost
A tunnel project does not simply pause. Crews and equipment that stand idle still cost money, workers take other jobs, and the long-term financing depends on a steady drawdown of federal grants. A short stoppage therefore matters more than the days involved.
That is the larger worry the commission raised after the money returned. It warned that a future stoppage could follow if disbursements stopped again, and it continued its lawsuit to secure full access to federal funding. The lesson most people draw is that the project, which is paid for under an agreement splitting the cost between the federal government and the two states, depends heavily on the reliability of the federal share.
Why New Jersey cares
A commuter on the Northeast Corridor, the Morris and Essex lines or the North Jersey Coast Line, goes into Penn Station through the same tunnel as everyone else. A failure of one tube, even a short one, shows up as cancellations across the state. In that sense the Gateway project is less about adding trains than about protecting the ones that exist. The fourteen NJ Transit rail lines, explained shows how much of NJ Transit's system funnels into that single crossing, and Secaucus Junction: the hub built in the Meadows looks at the junction where many lines come together before the tunnel.
It is also a New Jersey construction story, since the surface alignment contract covers the approach on this side of the river. NJ Transit's operating money is a separate matter, covered in NJ Transit's 3% increase and the record $3.5 billion budget.
What to watch next
Three things will tell you whether the pause was a one-time event or the start of a pattern.
- Reimbursement pace. Federal payments arrive as the commission submits requests for work already done. Delays in those payments are the early sign of trouble.
- The boring schedule. With the Hudson River contract awarded in April, the next milestone is the start of boring under the river. A schedule that holds is a sign of confidence.
- The 2035 target. The commission still points to about 2035 for the second tunnel. Any slip in that date will show up first in the commission's public board materials.
The commission publishes its board agendas and project updates at gatewayprogram.org, and NJ Transit lists service alerts on its own site. For how the trains themselves run, see Riding NJ Transit: trains, buses and light rail. The tunnel will not change a commuter's day for years, but it is the work that makes repairs to the old tubes possible.